How long does custom jewelry production take — the ranges
For an order built from scratch — from sketch to finished batch — the realistic lead time is 6–12 weeks. A repeat of a design that already has a model and a mould usually closes within 2–4 weeks. Short trial runs can be ready in three weeks; large volumes with several finishes may take a full quarter.
Jewelry production is a chain of operations, and each stage has its own technological time — some of it, like casting cool-down or plating thickness control, simply cannot be shortened by a commercial decision.
Stage 1: design and 3D model — 1–3 weeks
If we receive a production-ready file, this stage disappears. If we start from a sketch, photo or description, 3D modelling is needed, usually with two rounds of revisions. The model itself takes 3–7 working days; the rest is client-side approval.
This is where schedules slip most often — not because of technology, but because the decision on shape arrives a week later than assumed. Agree upfront who on the brand side approves the design.
Stage 2: mould and casting — 2–3 weeks
Once the model is approved, a master and mould are made. Lost-wax casting requires building a wax tree, investing, burnout and only then pouring the metal. One flask cycle takes dozens of hours and does not shrink with a smaller order.
On a first run we add time for a trial cast — checking wall thickness, sprues and metal shrinkage. That one week saves a month of corrections later.
Stage 3: finishing and plating — 1–3 weeks
A casting is only a semi-finished part. Next come cutting, grinding, chasing, polishing, stone setting and engraving. This is the most labour-intensive part of the process and the only one we genuinely scale by adding people.
Finally electroplating — rhodium, gold, oxidising. Each bath is a separate load with separate thickness control. With several colour variants of one design this stage can double, because batches run through the line separately.
Repeat runs and restocks — 2–4 weeks
The biggest time saving appears with the second order of the same design. The 3D model, master and mould exist, casting and plating parameters are recorded in the technology sheet — only the production run itself remains.
That is why brands planning a permanent collection should treat the first order as an investment in tooling. Restocks are faster, cheaper per unit and — more importantly for a shop — repeatable in plating shade and finish, which keeps the range consistent in photos and on the shelf.
What usually extends the deadline
In our experience delays rarely come from production itself. The most common causes are:
- slow approval of the 3D model or sample;
- design changes introduced after the mould is made — always a restart of that stage;
- vaguely specified finishing ("polished" versus "satin" are two different processes);
- stones or components supplied by the client arriving late;
- season — autumn is the peak of Christmas preparation, and summer means holidays across the whole industry.
How to genuinely shorten lead time
The most effective step is preparing the enquiry so that quotation and schedule can be produced first time: metal and hallmark, finish, volume, dimensions, target date and any visual references. The fewer follow-up questions, the sooner stage one starts.
The second is splitting the order: a small trial run now, the main run after the design proves itself in sales. The model and mould already exist, so the second tranche leaves the line in 2–3 weeks instead of two months.
The third is planning ahead of the season. Brands that place Christmas orders in August receive goods calmly; those ordering in November pay for rush and still may not make it.
If you are planning custom jewelry production and need a firm date for your design, send us the project or a description — we reply with a schedule and a quote.